The airport in the Leningrad region was supplied with electricity

Rosseti Lenenergo specialists allocated an additional 700 kilowatts to the general-purpose airport located in the Leningrad region, the company’s press service said.

The main source of power supply was a 35 kW substation. For supply, specialists used 0.4 kV networks.

Power engineers have completed a number of works on the design and fit-out of a new complete transformer substation. As part of increasing the airport’s electrical power, specialists also installed two power transformers. The power of each one is 630 kilowatts, according to reports.Petersburg memoirs».

In addition, Rosseti Lenenergo employees built an overhead power transmission line and installed an intelligent system that tracks energy consumption.

The press service confirmed that they used exclusively Russian-made equipment.

In March, the Novoladoga Electric Networks subsidiary of Rosseti Lenenergo completed work on the restoration of a 35-kilowatt substation. The transformer kiosk supplies electricity to the cities of Otradnoye, the village of Pavlovo and a large enterprise that produces electrical products.